|
Komi Republic Oil Field Development, Russian Federation
Polar Lights and KomiArctic are oil field development projects located
in the Komi region in Russia. Both projects rely upon the severely degraded
Kharyaga-Usinsk pipeline. In early 1994 the pipeline began leaking, and
in August of 1994 a dike containing the leaked oil broke, spilling an
estimated 270,000 tons of crude oil onto the Arctic tundra. Projects receiving
EBRD support accounted for as much as 25% of the spilled oil. The Komi
spill was over three times the size of the Exxon Valdez disaster, making
it one of the largest releases of oil into the environment on record.
Environmental assessments and audits were commissioned by the Bank,
but they only covered the project sites and excluded the pipeline. Had
the EBRD assessed the pipeline, it is unlikely the projects would have
been approved by the Board. CIEL's requests for copies of the EAs were
denied by both the Bank and the project sponsors. CIEL could only view
the Polar Lights EA at Conoco headquarters in Houston, Texas.
By supporting these projects, the EBRD has contributed to a major environmental
disaster. The Bank claims it had no control over the condition of the
pipeline, which was within the exclusive control of Komineft. Komineft,
according to the Bank, refused to even allow inspection of the pipeline.
It appears that the Bank did make efforts to include infrastructure improvement
as part of the projects, but the Russian government did not consent. At
that point, the EBRD should have refused to make the loans.
After receiving a request for help in January 1995, the EBRD and the
World Bank agreed to jointly finance a US$140 million emergency loan to
fund cleanup efforts. While the spread of the spill appears to be temporarily
in check, additional ruptures have appeared in the pipeline, and the temporary
containment dikes will be further tested by seasonal floods. The Komi
spill demonstrates, in the starkest terms, the need to implement the EBRD's
mandate for sustainable development.
Promising New Directions in Bank Lending
In the past year the EBRD has begun several promising new initiatives.
Chief among these are two new departments within the Bank, the Energy
Efficiency Departmentand the Municipal and Environmental Infrastructure
Department. The Bank has also explored some innovative financing mechanisms
for environmental investments, including environmental loan guarantees
and "green equity."
The Energy Efficiency Department
Despite the tremendous savings and environmental benefits that can be
obtained from energy efficiency, less than 3% of the EBRD's energy sector
lending has been for demand-side efficiency. The Bank has finally recognized
this problem and established the Energy Efficiency Department (EED) in
October of 1994 to identify and develop energy efficiency projects. In
its first year of operation, the EED developed several different types
of programs and projects, including direct investments in energy efficiency
technology, dedicated credit lines for energy conservation, and regional
multi-project facilities.
The market for energy efficient technologies for the Bank's countries
of operation is quite large, with estimates ranging from US$40 to US$55
billion. How successful the EED will be in tapping this potential market
is not clear, although projected funding levels for EED projects are encouraging.
The EED is precisely the type of initiative needed for the Bank to fulfil
its mandate to promote environmentally sustainable development.
Municipal and Environmental Infrastructure Department
In June of 1995 the Bank created the Municipal and Environmental Infrastructure
Unit to take charge of the Bank's environmental programs. The Bank currently
has two regional environmental programs, the Baltic Sea Programme and
the Danube River Basin Environmental Programme. The Baltic Sea Programme
is a joint effort by Baltic countries to address the sewage, industrial,
and hazardous waste currently being discharged into the Baltic by investing
in environmental infrastructure, environmental policy development, and
institutional reform. The Danube River Basin Environmental Programme,
which was formed to identify and address the heavy pollution discharge
from the Danube into the Black Sea, establishes an integrated strategic
management plan for improving the environment of the river basin.
The Bank has signed four water treatment projects as part of the Baltic
and Danube programs: a 23.4 million ECU loan to improve water supply and
waste water management in Tallinn, Estonia; a 10.6 million ECU loan to
rehabilitate waste water treatment facilities in twelve other Estonian
municipalities; an 11.5 million ECU loan to assist the municipal water
authority in Kaunus, Lithuania; and a 22.8 million ECU loan to upgrade
the water supply and waste water treatment facilities in five Romanian
municipalities. The Bank has also commissioned a number of regional and
sectoral studies and initiated several technical cooperation projects
in the participating countries.
Environmental Financing Initiatives
Recently the Bank has used several other creative mechanisms to help
finance environmental projects. It maintains the Secretariat of the Project
Preparation Committee, which coordinates funding from donor countries
and international financial institutions for environmental projects in
the region. The EBRD also chairs the Working Group on Environmental Project
Financing , which is investigating ways to enhance environmental investments
through such innovative measures as environmental loan guarantees and
"green equity."
The EBRD Environmental Procedures
The EBRD Environmental Procedures were adopted in January of
1992. Discussions with NGOs throughout the preceding year led the Bank
to strengthen the procedures in a number of areas. Still, they fall far
short of what is needed to achieve sustainable development, particularly
in the areas of information disclosure and public participation.
In practice, the Bank sometimes cuts corners in implementing its Environmental
Procedures or ignores them altogether, often as a result of perceived
time constraints or financial pressures on the borrower. By failing to
follow its procedures, the Bank sacrifices environmental protection for
expediency and undermines its own commitment to rule of law.
Purpose of the Environmental Procedures
The Environmental Procedures are intended to guide Bank staff
in exercising environmental due diligence to ensure that each project
is environmentally sound. More specifically, they aim to ensure that decisions
to approve or disapprove projects are made with awareness of each project's
environmental implications; to avoid potential environmental liabilities;
to account for environmental costs as well as other costs and liabilities;
and to identify opportunities for environmental enhancement. (EBRD, Environmental
Procedures (adopted Feb. 13, 1992) at iii.)
These aims, while important, are not adequate to ensure that Bank-financed
projects will be consistent with the Bank's mandate to promote sustainable
development. The Environmental Procedures provide no substantive
guidance as to the types of projects that will contribute to sustainable
development and those that should be avoided, nor do they require the
integration of environmental considerations into the earliest phase of
project identification, selection, and design. Rather, environmental consequences
are considered on a project-by-project basis, often with little apparent
regard for the cumulative and indirect effects they may have on the environment.
A review of the Bank's environmental assessment and project approval
processes reveals that the Bank does not always meet even the limited
aims of its Environmental Procedures . Relatively few projects
are subjected to full EA, even when they clearly appear to fall within
the Bank's list of projects requiring full EA or within similar lists
in national EA laws.
Procedures for Environmental Assessment
The EA process is the principal mechanism for evaluating a project's
environmental consequences and is critical for implementing the goals
of sustainable development. According to the EBRD Environmental Procedures
, the project sponsor is responsible for preparing the EA. Project sponsors
frequently lack experience with EAs and may fail to develop and release
important information or attempt to limit the participation of concerned
citizens and NGOs.
It is difficult to assess whether project sponsors withhold or fail
to develop significant information about potential adverse impacts. Consultants
conducting EAs have occasionally been prevented from reaching conclusions
because of lack of data. Whether this is due to the haste with which some
assessments have been prepared or to the deliberate withholding of information
by the project sponsor, it is unacceptable.
Initiation and Screening
Initiation and screening occur at the earliest point of the environmental
investigation--when the need for an environmental assessment or environmental
audit is determined. During screening, the Environmental Staff should
ascertain the purpose and need for the proposed project, identify
tentative alternatives, and determine the appropriate level of environmental
review. Based on preliminary environmental information provided by the
project sponsor, the staff must decide whether a proposed project will
require full EA, some intermediate level of assessment, or no assessment
at all.
During screening, the staff assigns each project an A, B, or C to designate
the level of assessment the project is to receive and 0 or 1 to indicate
whether an environmental audit is required. Bank staff are guided in screening
by lists of specific types of projects for which the level of assessment
is predetermined. These lists are intended to provide examples only and
do not preclude assessment of unlisted projects.
If a project is designated to receive a different level of assessment
under Bank procedures than under national law, the Environmental Procedures
state that the more stringent of the two listings determines the level
of assessment. Nevertheless, many projects have been screened into Category
B even though they either are listed by the Bank as Category A-type projects
or require full EA under national law. Sometimes projects are screened
into Category B even when full assessment is required by both Bank
procedures and national law.
The Environmental Staff has explained that more projects are not screened
into Category A partly because many Category B projects receive environmental
audits, which uncover much of the information that would be sought in
an assessment. This explanation ignores the different purpose and nature
of environmental assessments and environmental audits. The Environmental
Procedures clearly state that one cannot substitute for the other.
Furthermore, audits are not made public and provide no opportunity for
public participation.
The difference in treatment between Category A and Category B projects
is significant. Projects screened into Category B receive a lower level
of assessment and do not require that the public participate in, receive
information about, or even be notified about the assessment.
Scoping
Scoping is a process for creating a dialogue between the project sponsor,
government officials, and the public to determine the scope of the environmental
assessment. It should be an open process designed to ensure that important
issues are identified early in the EA process.
The Environmental Procedures only require scoping for Category
A projects. They identify four types of actions involved in the scoping
of an EBRD EA: identifying known environmental issues; identifying the
concerns of all interested parties; setting up meetings between interested
parties; and preparing the Terms of Reference and selecting experts to
undertake the EA. In addition, environmental assessments should
include the analysis of environmental costs in economic terms.( Id.
at 30-31. )
As illustrated by the ZSNP and Mochovce case studies, project sponsors
have not consistently fulfilled these requirements. The ZSNP aluminum
smelter project included no public scoping whatsoever. The project sponsor
for the Mochovce nuclear power plant project made only a minimal effort
to comply with the Bank's requirements by sending a draft table of contents
for the EA to a number of NGOs for comment. The general public was not
notified about the project and had no opportunity to comment during scoping.
Alternatives
The importance of investigating alternatives to the proposed activity
cannot be overstated. In fact, most environmental assessment laws, including
the laws of Central and Eastern Europe, require a thorough analysis of
alternatives, including the important "no-action" alternative.
To generate alternatives, it is necessary to define, at the earliest
stage of the EA, the purpose and need of the proposed action. All
alternatives that would fulfil thepurpose and need should be considered
in the EA. The purpose and need should be stated broadly to avoid
excluding desirable alternatives. The no-action alternative should be
included to provide a baseline for comparing and contrasting the impacts
of other alternatives, including the proposed action.
The EBRD's Environmental Procedures do not require that the EA
contain a statement of purpose and need, and it is unclear whether
the EA must identify and discuss alternatives to the proposed action.
Without alternatives, EAs cannot identify the least-cost approach, which
is very important in energy planning, where energy efficiency and conservation
are frequently less expensive than building new generating capacity. The
EAs CIEL has examined do not discuss least-cost.
The least-cost study for Mochovce was conducted independently of the
EA. As a result, it did not consider all the impacts of the project, and
could not account for all environmental and social costs associated with
the proposed project and its alternatives.
Impacts
EAs should evaluate three types of impacts: direct, indirect, and cumulative.
Indirect and cumulative impacts can be as severe as direct impacts, but
are often more difficult to identify, making their consideration in the
EA all the more important.
EBRD EAs do not explore all foreseeable indirect and cumulative impacts,
even when they may be very significant. For example, the EAs for the KomiArctic
and Polar Lights oil field development projects in Russia did not include
an assessment of the Kharyaga-Usinsk pipeline, even though it was widely
known that the pipeline was leaking badly and might rupture. Had the pipeline
been included in the EAs, it seems highly unlikely the project would have
been approved by the Board.(Bank staff say the pipeline was not included
in the EA because it was not within the project boundaries. But the procedures
clearly state that one reason to conduct an environmental assessment is
to identify impacts outside the area occupied by the project. EBRD, Environmental
Procedures 26 (adopted Feb. 13, 1992). The EBRD is planning to prepare
a full EA for the Chernogorskoye oil field development project in the
near future. Incredibly, the Environmental Staff cannot say whether that
EA will include assessment of the pipeline.
Assessment of global impacts relating to such global environmental problems
as climate change and depletion of the ozone layer is now required by
a growing number of countries and institutions, including the World Bank.
The EBRD, however, does not require that global impacts be assessed in
its EAs.
Mitigation and Remediation
Having examined all reasonable alternatives that satisfy the purpose
and need, and their impacts, the EA must identify mitigation and remediation
measures to reduce adverse impacts and enhance beneficial ones. EBRD EAs
often contain detailed recommendations for mitigating identified adverse
impacts and remedying existing environmental damage. The Bank appears
to take these recommendations seriously, frequently requiring mitigation
and remediation that should significantly improve the environmental performance
of projects it finances.
Mitigation and remediation needs that are identified as necessary during
environmental review may either be incorporated into loan agreements as
covenants or contained in a separate remediation agreement. The ZSNP project
involved both types of agreements. Originally, the Bank planned to sign
the loan agreement and disburse the first tranche of funds for ZSNP before
the remediation agreement was completed and signed. As the project sponsor
would already have achieved its main objective, this would have eliminated
the borrower's main incentive to undertake potentially costly mitigation
and remediation measures. However, due to complications apparently unrelated
to remediation, the loan agreement was delayed and was finally signed
at the same time as the remediation agreement, nearly a year after approval
by the Board.
The draft agreement generally responds to the environmental recommendations
contained in the ZSNP environmental assessment and audit, but it lacks
the specificity which is needed for proper implementation and enforcement
of environmental actions. For example, the agreement stipulates that a
bentonite wall must be built around the "red mud" waste pile, but it neglects
to incorporate the recommendation of the assessment that it encompass
the fly ash area, which is suspected of leaching arsenic.
It is also troubling that the Bank is unwilling to make the remediation
agreement public, especially since the Bank proposes to include the public
in post-completion monitoring of ZSNP. The Bank gave the project sponsor
veto power over public dissemination of the agreement.
Environmental Audits
The EBRD uses environmental audits to determine the likelihood and extent
of potential liabilities at sites with ongoing operations or which require
property transfer. For existing operations, audits also assess compliance
with applicable environmental laws and regulations. The decision whether
an audit is necessary is made at the screening level. The Environmental
Procedures differentiate between environmental audits and assessments,
stating that "they address different concerns, and are in no way substitutes
for each other." Projects frequently require both kinds of investigation.
The project sponsor must develop a Management Action Plan that addresses
the conclusions and recommendations of the audit. The Environmental
Procedures do not require the Environmental Staff to evaluate and
recommend changes to the plan, however, or to monitor its implementation
Environmental audits provide no avenues for public participation, and
the Bank does not disclose audit results. There is no mechanism comparable
to scoping for environmental audits, and the section of the Environmental
Review Memorandum which evaluates the adequacy of public participation
does not apply to environmental audits. Audits which require additional
phases of investigation appear to be similar in scope to full EAs. In
these cases, especially where contamination has been identified, there
is no rationale for prohibiting full public disclosure and participation.
To continue click HERE
|