|
Procedures for Project Review and the Environmental Veto
Under the current Environmental Procedures, the Bank has two
reviews during which environmental information is discussed and projects
can be rejected on environmental grounds. In neither review, however,
does the Environmental Staff have control over the decision. The Staff
can recommend that a project not proceed for environmental reasons, but
the decision lies with the Operations Committee, the President, or ultimately
the Board of Directors.
During Initial Review the Environmental Staff may recommend that the
project be rejected "if there are major potential environmental concerns
associated with the project which are not likely to be overcome during
project preparation." This is a recommendation only; the decision whether
to proceed rests with the entire Operations Committee.
At Final Review the Operations Committee examines the environmental
information contained in the Investment Proposal. The Environmental Staff
may recommend that the project not proceed "if the environmental issues
have not been properly addressed by the project sponsor or if the potential
impacts are too great."
In cases of disagreement between the Environmental Staff and the Team
Leader as to whether a project should proceed, there are three levels
of recourse. First, the question is discussed at a meeting between the
Environmental Staff, the Senior Environmental Specialist, and the Team
Leader. If they are unable to resolve the disagreement, it may be reviewed
by the Operations Committee. Finally, if the disagreement persists, it
may be resolved by the President of the Bank.
In the event of such an impasse, the Environmental Advisory Council
(ENVAC) could play a useful role by reviewing the dispute with Bank staff
and providing advice to the President. But in the end, if the projected
net environmental outcome of a proposed project would result in a significant
loss of environmental quality or would not promote sustainable development,
the Environmental Staff should have authority to veto the project.
Procedures for Board Decision-making
The final decision whether to proceed with a project rests with the
Board of Directors, after review by the Executive Committee. A cardinal
rule of environmental assessment is that the resulting document must be
available to the decisionmaker before decisions are made and irreversible
actions are taken. Information provided to the Board is useful only if
the Board has sufficient time to review it. For this reason, CIEL supports
the "Pelosi Amendment," which prohibits the U.S. Director from voting
to approve any project that may have substantial environmental impacts
unless an EA has been made public 120 days in advance of the vote.
The Board of Directors should reject projects where corners have been
cut in project preparation, where data is not available to the EA preparer
or the Board, or where the Environmental Procedures, particularly
those for public participation, have not been strictly followed.
One EBRD project--the Chernogorskoye Oil Field project in Russia--was
approved by the Board before a full EA was completed. The Board approved
the loan subject to the performance of a full EA, satisfactory to the
Bank. However, the Board will not have an opportunity to review the EA
and reject the project if the results are unsatisfactory. Moreover, by
the time the EA is completed, nearly 50% of the funding for the project
will have been disbursed, seriously prejudicing future decisions.
The Board should check periodically to see that EBRD staff is providing
all relevant information. A key document submitted by the Environmental
Staff to the Board just prior to its decision to approve the controversial
ZSNP loan contained inaccurate information
The Polar Lights and Komi projects also demonstrate the need for greater
oversight of the Bank staff. Allotting more time for Board members to
examine the complex and substantial amount of information submitted with
each project would provide an opportunity to validate the assertions made
by Bank staff and project sponsors. The establishment of an Independent
Inspection Panel would give the public the opportunity to assist the Board
in this supervision.
Procedures Related to Monitoring and Evaluation
The current Environmental Procedures for monitoring and evaluating
environmental aspects of projects, if carried out diligently, will help
ensure that mitigation and remediation measures are fully implemented
and that projects are environmentally sound. They will also provide important
environmental data that will contribute to the design of future projects.
Monitoring and evaluation are carried out at three stages of the project
cycle: during project execution, upon project completion, and for some
large-scale projects, after project completion. One progressive element
of the Environmental Procedures is the requirement that EAs contain
a monitoring plan. In this respect the procedures go beyond many national
EA laws. Unfortunately, it appears the Bank fails to enforce this requirement,
as the EAs that we have reviewed do not contain such a plan.
If monitoring discloses that the project sponsor is not in compliance
with covenants in the loan agreement, the Bank can impose penalties, which
may include freezing disbursements and notifying proper authorities and
other financial agencies and co-financiers. When a project is completed,
the Bank's Environmental Staff must assess environmental aspects of the
project. The resulting Environmental Evaluation Memorandum discusses whether
the impacts of the project were adequately anticipated in the EA and evaluates
the effectiveness of mitigation measures undertaken by the project sponsor.
It is not possible to assess the Bank's monitoring efforts, as the Bank
does not publish monitoring plans. The bank should require a monitoring
plan in every EA. The Bank should also strengthen its capacity for supervising
environmental performance by withholding a portion of the loan until mitigation
and remediation requirements have been fulfilled.
The Draft Revised Environmental Procedures
In August 1995, after more than a year of revision, the Bank released
itsDraft Revised Environmental Procedures. CIEL had hoped that
the new procedures would mark a positive change in the Bank's commitment
to sustainable development and environmental due diligence. Unfortunately,
we find the Draft Procedures to be a disappointment. They contain
a few improvements, but overall we find them to be even less stringent,
detailed, or clear than the existing procedures.
Screenin
Two different screening options are proposed under the Draft Procedures.
Option 1 is similar to the current screening procedure. Option 2 would
give the Environmental Staff more discretion; instead of consulting lists,
the staff or project sponsor would conduct an Initial Environmental Examination
to determine whether a full EA is required.
Option 1 is preferred, as the staff already exercises too much discretion
in screening projects. Clear, mandatory guidelines would also be more
amenable to review by an Independent Inspection Panel.
Scoping
The Draft Procedures merely require the project sponsor "to ensure
through a scoping process that, prior to initiating environmental investigations,
the key issues that need to be appraised, and the way the public will
be involved in the appraisal, have been identified." They require contact
with the "locally affected public" and government agencies, but the involvement
of local and national organizations is optional. No mention is made of
international NGOs. Scoping meetings are also optional.
These scoping procedures are far too general; they require more detail
and should be mandatory. Contact should not be restricted to the locally
affected public, as some impacts may be regional or global. Scoping meetings
should be mandatory.
Alternative
The Draft Procedures omit consideration of environmental costs
of proposed projects from EAs, a critical defect. There are also some
improvements. The EA must include a statement of purpose and need
and an assessment of the "no-action" alternative.
Impacts
The Draft Procedures call for identification of indirect impacts,
but do not mention cumulative impacts. The Environmental Screening Memorandum
must identify regional and global impacts, but there is no requirement
that they be considered in the environmental assessment.
Mitigation and Remediation
The Draft Procedures provide for an Environmental Action Plan
(EAP) to be developed by the project sponsor. It documents "key issues,
actions to be taken to adequately address the key issues, the implementation
schedule and timescale, and an estimate of the associated costs." Despite
being written in permissive, rather than mandatory, language, the EAP
is a welcome addition to the EBRD's Environmental Procedures .
Unfortunately, the entire EAP process could be undermined by the failure
to provide for public participation or even publication of the EAP.
Project Review
The Draft Procedures appear to weaken the authority of the Environmental
Staff in the project approval process. There is no provision for Staff
even to recommend that a project be rejected on environmental grounds.
Staff should have a mandatory veto.
Board Decision-making
The Draft Procedures provide a 30 day minimum time period between
the release of the EA to the public for comment and submission to the
Board. This time period can be waived upon sufficient showing by the project
sponsor. Thirty days is far too short a period for public comment. There
should be a non-waivable minimum 90 day period for comments and the full
120 days required by the Pelosi Amendment from the date the EA is released
to the time the project is submitted to the Board.
Monitoring
The Draft Procedures stress the importance of monitoring during
and after project execution, but do not specify when projects require
monitoring. No provision is made for the staff, or a third party appointed
by the staff, to conduct monitoring. The sanctions for non-compliance
(freezing disbursements and notifying proper authorities) have been eliminated,
as has the Environmental Evaluation Memorandum. Provisions for release
of monitoring information and public consultation have been added but
these provisions are recommendatory only.
Public Participation and Access to Information
The charter of the EBRD commits the Bank to "fundamental principles
of democracy, the rule of law, respect for human rights, and market economies."
First and foremost among democratic principles are the rights of all citizens
to be informed of, and to participate in, decisions affecting their well-being.
Disclosure of Information to the Public
The EBRD's approach to information disclosure does not reflect its stated
commitment to public participation throughout the project cycle. The Bank
refuses to provide any project-specific information to the public, requiring
instead that all information come from project sponsors or be released
with their permission.
Reliance on the project sponsor to release information to the public
has several serious defects. First, project sponsors in the Bank's countries
of operation often have little or no experience managing a public participation
program and have frequently shown a reluctance to release information
to the public. The ZSNP project sponsor continues to block release of
the remediation agreement. Initially, the Mochovce project sponsor would
only release summaries of the least-cost study and the nuclear safety
report. Neither made any information available during the scoping phase.
Second, the requirement in the Environmental Procedures that
EAs of Category A projects be made available to the public is often not
followed in practice. CIEL's requests for copies of the Polar Lights and
KomiArctic EAs were denied.
Third, what little information project sponsors provide to the public
comes too late in the project cycle to enable the public to participate
effectively in the decision-making process. NGOs and citizens that participate
in scoping or submit comments during the preparation of the EA frequently
must do so only on the basis of what limited information they are able
to obtain through their own resources.
Fourth, information contained in some documents, such as Environmental
Screening Memoranda and Environmental Evaluation Reports is unavailable
elsewhere. There is no legitimate reason for the EBRD, or its project
sponsors, to withhold environmental information from the public or to
fail to provide such information in a timely manner. All parties seeking
Bank financing should understand this to be a requirement of the loan
application. While some information may properly be considered confidential
for reasons of national security or to protect commercial secrets, there
should be a strong presumption in favor of releasing all information.
The Board of Directors should condition the approval of all loans upon
full access of the public to such information.
Other international financial institutions have begun to recognize the
need for transparency. Under the new World Bank Policy on Disclosure of
Information, there is a presumption in favor of disclosure. Information
on World Bank activities is made available through the newly formed Public
Information Center.
The guiding principle of the InterAmerican Development Bank's new policy
on information disclosure is that "documents should be made available
to the public on request in the absence of a compelling reason for confidentiality."
It explicitly provides for frequent public notification and consultation
throughout the project cycle. The Asian Development Bank's new information
policy establishes a similar presumption in favor of disclosure.
The International Finance Corporation, which works primarily with private
companies, has committed in its information disclosure policy to "undertake
its investment activities with transparency and accountability." The IFC
policy presumes disclosure of information unless it would "materially
harm the business and competitive interests of clients." The IFC makes
this information available through the World Bank's Public Information
Center.
In contrast, a proposed EBRD information disclosure policy emphasizes
the importance of maintaining client confidences and protecting the integrity
of Bank staff. A Project Summary Document similar to the IFC's Summary
of Project Information would be made available to the public, but only
after the project has been approved by the Board of Directors (the
IFC makes its document available a minimum of thirty days before submission
to the Board). It would only contain information not found to be "confidential"
or "harmful." Environmental information about Category B projects would
continue to be unavailable.
This new policy would not help the public influence EBRD projects or
ensure their proper development. Rather than promoting a culture of secrecy,
the EBRD should vigorously implement its commitment to democracy, and
become a leader, both in the region and among financial institutions,
in promoting transparent and democratic decision-making.
Public Participation in Environmental Assessment
The Bank's current procedures for public participation are the product
of more than a year of negotiation between Bank officials and NGOs. As
a direct result of these efforts, citizens have the right to participate
in and comment on EAs, and the Bank must take their comments into account
when approving a project. Unfortunately, the Environmental Procedures
fail to provide adequate guidance to project sponsors and omit some very
important elements. The public participation requirements are written
so generally that even a good faith effort by a project sponsor to comply
may fall far short of what is needed.
Notification to the Public
Early notification is essential for the public to participate effectively
in scoping. Notification to the public should take place at the onset
of environmental assessment, so that all interested parties--citizens,
governmental agencies, NGOs, and relevant community organizations--will
have an opportunity to raise issues they feel should be addressed in the
EA. More particularly, notification should occur prior to screening so
that all citizens wishing to participate in the full EA process will have
an opportunity to do so.
The Environmental Procedures only require notification when the
project has been classified Category A or where required by national law.
Like most aspects of EBRD environmental assessment, notification is the
responsibility of the project sponsor. The procedures do not provide any
guidance on how to conduct notification or determine who is sufficiently
"affected" to require notification.
Notification requirements have not routinely been followed by project
sponsors. The Mochovce EA commenced with virtually no notification to
the public. Only a few NGOs were informed of the start of the EA process.
They received only a draft table of contents, with no information about
the project, its purpose and need , or possible alternatives. The
ZSNP EA process dispensed with public notification altogether.
The EBRD Environmental Staff should ensure effective notification takes
place by providing a timetable and helping the project sponsor formulate
a notification strategy. The strategy should identify all potentially
interested parties, methods for notifying those parties, and the information
needed for effective participation. Notification should include enough
information to let parties know whether the project is of interest to
them. At a minimum, it should describe the proposed action, its purpose
and need, tentative alternatives and impacts, and the proposed scoping
process.
Public Participation in Scoping
The Environmental Procedures fail to provide sufficient guidance
as to what information is to be provided to the public prior to scoping
and leave it to the project sponsor to determine what constitutes an "appropriate
level" of public consultation. As a result, project sponsors have not
involved a sufficient number of affected parties in the process; have
failed to provide adequate information to ensure informed participation;
have limited public comments on the scope of the EA--excluding from consideration
such topics as alternatives, impacts, and mitigation; and have not conducted
effective public scoping meetings.
Project sponsors for the ZSNP and Mochovce projects virtually dispensed
with public participation during scoping. The ZSNP project included no
public scoping whatsoever. The project sponsor for Mochovce made only
minimal efforts to comply with the Bank's scoping requirements.
In the one meeting the project sponsor held to discuss scoping of the
Mochovce EA, only a few NGOs were allowed to participate. They received
just one week's notice of the meeting, with no information about the agenda
or the project, beyond a revised table of contents for the EA. It appears
that, by the time of this meeting, the EA was well under way and that
the scope of the EA had already been set by the terms of reference. In
particular, the project sponsor was not prepared to discuss alternatives
to the project. NGOs that attended the meeting also expressed frustration
that no representatives from the EBRD were present, as a number of questions
they raised could not be answered by either the project sponsor or the
consultants hired to prepare the EA. The NGOs were told they should address
those questions to the EBRD.
Both ZSNP and Mochovce illustrate the need to expand and clarify procedures
for public participation during scoping, and to create a mechanism, such
as an Independent Inspection Panel, to enforce these new requirements.
The Environmental Procedures should be strengthened to require
the project sponsor to open the public participation process to all interested
parties, not just those chosen by Bank staff or project sponsors. Procedural
requirements, including a minimum period for public comment, are needed
to ensure that the public has both the time and opportunity to develop
and express their concerns.
Receipt of Comments and Opinions from the Public
The public should have the opportunity to provide comments on a project
at any point during the project cycle, but three points are particularly
important: during scoping, upon release of the draft EA document, and
between release of the final EA document and decision by the Board.
Scoping gives the public an opportunity to identify areas of concern,
suggest alternatives, and discuss impacts and mitigation. The comment
period after the draft EA document is released provides the public with
an opportunity to review the document carefully and raise issues and alternatives
that are not included or satisfactorily addressed. The comment period
after the final document is released gives the public an opportunity to
review the document to make sure it addresses all comments and resolves
all outstanding issues.
The current Environmental Procedures provide very limited opportunity
for public comment and do not require the project sponsor to respond to
comments. The procedures merely state that comments and opinions expressed
by the public are to be taken into account in the project approval process.
No explicit provisions are made for the public to comment on either a
draft or final EA, no public meetings are required, and no comment period
is specified. Perhaps most troubling, the project sponsor is not required
to publish the public's comments in the EA report or to respond to comments
either by modifying the EA or explaining why the comments do not warrant
further response.
Public comment was virtually absent during the ZSNP project cycle. The
EA was not provided in draft form for comment, no public meetings were
held during its preparation, and only hurried, last minute meetings were
held with a select group of NGOs prior to submission of the project to
the Board. The NGOs that participated were informed of the meeting only
days before it occurred and were not given documents in advance of the
meeting. Consequently, they could not participate effectively.
The process for commenting on Mochovce, while better than ZSNP's, was
still flawed. Problems with commenting during scoping have already been
discussed. In addition, the project sponsors neglected to provide an opportunity
to comment on the draft EA, and the seventy day period for comments on
the final EA, least-cost study, and safety report were too short, especially
since many groups received these documents late.
Public Participation in Implementation and Monitoring
Continued public consultation and monitoring is necessary both during
project implementation and after the project is completed to ensure that
the project sponsor complies with the environmental conditions of the
loan and that otherwise unforeseen environmental consequences are properly
addressed. For the public to participate effectively, it must have access
to project information, loan conditions, and remediation agreements. Under
the current Environmental Procedures, these documents are not made
public. In comparison, other multilateral development banks, notably the
World Bank and the IDB, continue to provide and update project information
after its approval, including loan documentation and mitigation proposals.
To compensate for failing to implement its public participation procedures
on the ZSNP project, the Bank proposed the creation of a Monitoring and
Advisory Group to give the public a role in monitoring the project. Unfortunately,
prospects for the success of this exercise appear somewhat doubtful. It
started on the wrong foot. The terms of reference were drafted by the
Bank without public input. Surprisingly, neither the terms of reference
nor the remediation agreement will be made public. NGOs have expressed
reluctance to participate, fearing their participation might be perceived
as an endorsement of the project. In spite of these problems, the Monitoring
and Advisory Group still has significant potential to advance public participation
in monitoring.
To contine click HERE
|